Q) The scope management plan is a subsidiary of which the project document?
una) Schedule management plan
si) Plan de gestión de proyectos
do) quality management plan
re) resource management plan
Q) Which is an example of Administer purchases?
una) Contract negotiation
si) Authorization of companies Activities
do) Develop Statement of Work
re) Establishing evaluation criteria
Q) A process input Create WBS is a:
una) paper project.
si) register of interested parties.
do) Statement of the project’s purpose.
re) requirements traceability matrix.
Q) An input of the control is the planning process:
una) resource calendar.
si) task list.
do) Risk Management Plan
re) organizational process assets.
Q) The scope verification process mainly deals with:
una) formalizing acceptance of the completed project deliverables.
si) the accuracy of the work deliverables.
do) formalizing the approval of the budget sphere.
re) accuracy of the work breakdown structure (EDT).