Register Now

Login

Lost Password

Lost your password? Please enter your email address. You will receive a link and will create a new password via email.

Add post

You must login to add post .

Add question

You must login to ask a question.

Login

Register Now

Welcome to Scholarsark.com! Your registration will grant you access to using more features of this platform. You can ask questions, make contributions or provide answers, view profiles of other users and lots more. Register now!

CAPM Certified Associate in Project Management Exam Part-2

CAPM Certified Associate in Project Management Exam Part-2

Price: $94.99

Sample Questions

Q) The scope management plan is a subsidiary of which the project document?

a) Schedule management plan

b) Project Management Plan

c) quality management plan

d) resource management plan

Q) Which is an example of Administer purchases?

a) Contract negotiation

b) Authorization of companies Activities

c) Develop Statement of Work

d) Establishing evaluation criteria

Q) A process input Create WBS is a:

a) paper project.

b) register of interested parties.

c) Statement of the project’s purpose.

d) requirements traceability matrix.

Q) An input of the control is the planning process:

a) resource calendar.

b) task list.

c) Risk Management Plan

d) organizational process assets.

Q) The scope verification process mainly deals with:

a) formalizing acceptance of the completed project deliverables.

b) the accuracy of the work deliverables.

c) formalizing the approval of the budget sphere.

d) accuracy of the work breakdown structure (WBS).